Last modified: May 28, 2020
Court 13 July 6 to July 24
Court 14 June 22 to July 3
Court 15 May 18 to June 5
Court 16 June 8 to June 19
Door painting will be done around the end of the project—date TBD.
The upper areas requiring a lift to paint shall be scheduled from July 27 – August 7 in sequence 13, 14, 15, 16.
Last modified: May 28, 2020